Alternating lane closures scheduled for signal upgrades in Alexandria and Pineville

The Louisiana Department of Transportation and Development (DOTD) advises motorists that alternating lane closures are scheduled to begin Monday, July 13, as part of the District 08 Flashing Yellow Arrow Upgrade Part 2 project.

Weather permitting, alternating lane closures will be in effect from 9 a.m. to 4 p.m. beginning July 13 at the following intersections. One lane in each direction will remain open at all times:

  • US 165 (Masonic Drive) at Horseshoe Drive
  • US 165 (Masonic Drive) at South MacArthur Drive (Service Road)
  • MacArthur Drive at Sugar House Road
  • Broadway Avenue at Dallas Avenue

Beginning Tuesday, July 14, weather permitting, nightly alternating lane closures will be in place from 6 p.m. to 7 a.m. at the following intersections. One lane in each direction will remain open at all times:

  • LA 28 at Cloverleaf Boulevard
  • Eddie Williams Avenue and Broadway Avenue

The closures are necessary to allow crews to install new mast arms on signal pole foundations and perform related work.

DOTD anticipates work at these intersections will be completed by July 17, weather and other construction-related factors permitting.

The project was awarded to Jack B. Harper Electrical, LLC for $9,040,462.73.

There are no detours or lane width restrictions associated with the project.

DOTD reminds motorists that all construction activities are weather dependent and may be rescheduled in the event of inclement weather. Drivers are urged to use caution when traveling through work zones and watch for construction crews and equipment

The Louisiana Department of Transportation and Development (DOTD) advises motorists that alternating lane closures are scheduled to begin Monday, July 13, as part of the District 08 Flashing Yellow Arrow Upgrade Part 2 project.

Weather permitting, alternating lane closures will be in effect from 9 a.m. to 4 p.m. beginning July 13 at the following intersections. One lane in each direction will remain open at all times:

  • US 165 (Masonic Drive) at Horseshoe Drive
  • US 165 (Masonic Drive) at South MacArthur Drive (Service Road)
  • MacArthur Drive at Sugar House Road
  • Broadway Avenue at Dallas Avenue

Beginning Tuesday, July 14, weather permitting, nightly alternating lane closures will be in place from 6 p.m. to 7 a.m. at the following intersections. One lane in each direction will remain open at all times:

  • LA 28 at Cloverleaf Boulevard
  • Eddie Williams Avenue and Broadway Avenue

The closures are necessary to allow crews to install new mast arms on signal pole foundations and perform related work.

DOTD anticipates work at these intersections will be completed by July 17, weather and other construction-related factors permitting.

The project was awarded to Jack B. Harper Electrical, LLC for $9,040,462.73.

There are no detours or lane width restrictions associated with the project.

DOTD reminds motorists that all construction activities are weather dependent and may be rescheduled in the event of inclement weather. Drivers are urged to use caution when traveling through work zones and watch for construction crews and equipment.