School Board to consider two contracts’ change orders

By JIM BUTLER

The School Board is expected to approve almost $1 million in change orders for two construction projects at a special meeting today.

Both are the result of costs associated with addition of storm shelters – one at Alexandria Senior High, the other at L.S. Rugg Elementary.

The contracts are part of a bond issue approved several years ago for Wards 1 and 8 schools.

A $205,000 increase in the ASH contract will bring it to $12.58 million. Addition of 137 days takes substantial completion by MD Descant to December 2026.

The change includes that in the price of steel, an increase of $59,000 due to recent tariff increases, according to the supplier.

About 290,000 pounds of steel in 12 different products are called for in the construction specifications.

The Rugg shelter will add $775,000 to the school renovation project, also under contract with Descant.

The change brings the contract total to $4.4 million, extending substantial completion to March 15, 2026.

The board is also expected to award a contract for a Tioga High Fieldhouse. Bids were opened Monday afternoon.